The Law Amending Certain Laws ("Law No. 7554") has been published.
Law No. 7554 published in the Official Gazette dated July 24, 2025 and numbered 32965[1] (the "Law") introduced significant amendments to some of the main regulations on energy investments, environmental impact assessment processes, expropriation procedures and the execution of public services.
The aforementioned Law contains substantive and procedural amendments to various laws in order to eliminate various administrative and technical obstacles encountered in practice and to accelerate the efficiency of public services and investment projects. In the framework of this article, the main provisions of the Law will be discussed.
I. Amendments to Environmental Impact Assessment ("EIA") Processes
As a result of the amendment made by the Law to Article 10 of the Environmental Law No. 2872[2] ; the phrase "EIA is not required" has been removed from the text of the article, whereas it is explicitly stipulated that unless only an "EIA Positive Decision" is obtained, no approval, permit, incentive, building and use license, investment, and tender can be issued for the project.
On the other hand, with the new sentence added to the relevant article, it is also regulated that even if the EIA process has not yet been completed, this will not constitute an obstacle to applying for the relevant incentives, approvals, permits and licenses.
II. Amendments to the Mining Law
[3] The Law introduces comprehensive and multi-layered amendments to the Mining Law No. 3213. In this respect, some of the main issues are as follows:
- Rehabilitation Obligation and Rehabilitation Fee
The Law defines for the first time the concept of "rehabilitation" for the restoration of areas degraded as a result of mining activities, and regulates in detail the scope, financing and supervision of works to be carried out within this framework. In particular:
- Rehabilitation fees are to be deposited by license holders into special accounts to be opened at public banks;
- It is clearly regulated that these fees can only be used for rehabilitation purposes and cannot be attached, pledged or assigned;
- It is stipulated that the unused portion will be returned to the license holders whose rehabilitation obligation is no longer fulfilled.
In addition, it is regulated that production activities may be suspended in case of failure to fulfill the rehabilitation obligation; thus, the supervision and sanction mechanism regarding environmental sustainability has been strengthened.
- Provisions on Strategic and Critical Mines
The Law introduces the definitions of "strategic" and "critical" mines into the legislation and stipulates special procedures for these mines. Accordingly:
Critical minerals are minerals that may pose an economic or security risk in the event of a supply disruption or price increase;
Strategic minerals are defined as minerals that are of high importance for national security and economic prosperity and whose supply may be restricted.
It is stipulated that urgent expropriation can be made for mining activities related to strategic or critical mines within the scope of Expropriation Law No. 2942. On the other hand, it is stipulated that the determination of strategic or critical mines will be carried out by the Ministry of Energy and Natural Resources by taking the opinions of the relevant ministries and public institutions.
- Licensing, Permitting Processes and Collateral System
- In addition to license fees, rehabilitation fees have been made separate items and the procedures and principles regarding the collection and follow-up of these fees have been restructured.
- The obligation to convert letters of guarantee into cash and transfer them to the rehabilitation fee account has been introduced.
- Periods for the authorization processes have been determined; in some cases, it has been stipulated that the authorization will be deemed to have been granted upon expiration of the period even if the opinion of the institution is not obtained.
- The submission of an investment guarantee has been made mandatory for Group IV mines, and the tender and application systematics have been updated.
- Permission for Activities in Forest and Olive Groves
It is regulated that mining activities in state forests may be permitted free of charge, and that certain fees will be paid in case of subsequent transfer or operation of this permit.
With the Provisional Article 45 added to the Law, it has been made possible to grant limited permits for mining activities to be carried out in olive groves. Within this scope:
- The obligation of rehabilitation and the obligation to plant twice as many olive trees have been introduced, depending on whether the olive trees can be moved or not;
III. Amendments to Renewable Energy and Zoning Legislation
The Law introduces important facilitations to accelerate renewable energy investments and reduce bureaucratic obstacles:
- Pre-licensed wind and solar energy projects can be granted permits on forest immovable properties. In case a production license is obtained, this permission period can be extended until the end of the production license period.
- The period for urgent expropriation for renewable energy projects was extended until the end of 2030, and the President of the Republic was authorized to extend the period for another 5 years.
- Until the end of 2024, a "Production Facility Conformity Certificate" can be issued for facilities that have been commissioned but do not have a building license, if certain technical documents are submitted. This document will replace the license and no retroactive administrative sanctions will be imposed.
IV. Other Noteworthy Regulations
With the amendment to the Pasture Law[4] , the allocation of pasture lands for renewable energy investments has been made possible.
Ultimately, the Law aims to unify and accelerate environmental, economic and administrative processes by bringing together different topics under a single text. In this framework, important facilities have been introduced in many areas, especially in licensing and expropriation procedures, in order to ensure that energy, infrastructure and mining investments can be realized quickly and effectively.
In light of all these arrangements, the Law corresponds to a remarkable reform package in terms of eliminating obstacles to investment processes, ensuring efficiency in public services and increasing the deterrence of environmental inspections.
[1] For the relevant Law see:(https://www.resmigazete.gov.tr/eskiler/2025/07/20250724-1.htm)
[2] For the Environmental Law see: (Https://www.mevzuat.gov.tr/mevzuat?MevzuatNo=2872&MevzuatTur=1&MevzuatTertip=5)
[3] For the Mining Law see: (https://www.mevzuat.gov.tr/mevzuat?MevzuatNo=3213&MevzuatTur=1&MevzuatTertip=5)
[4] For Pasture Law see: (https://www.mevzuat.gov.tr/mevzuat?MevzuatNo=4342&MevzuatTur=1&MevzuatTertip=5)